Roundthorn Primary Academy — Internal Remodelling
Education2 weeks

Roundthorn Primary Academy — Internal Remodelling

Client
Roundthorn Primary Academy
Location
Oldham, Greater Manchester
Duration
2 weeks
Client Type
Primary School
SafeContractor

Internal remodelling works to reconfigure teaching spaces, including partition alterations, new flooring, ceiling works, and redecoration.

What Was Delivered

  • Classrooms refurbishment
  • Specialist sensory room installation
  • WC refurbishment
  • Mechanical engineering

What Made This Project Complex

  • 01Remodelling internal spaces within an occupied primary academy
  • 02Maintaining safe access for pupils and staff throughout
  • 03Phasing works to minimise disruption to teaching

The Challenge

Completing a full internal remodelling programme at Roundthorn Primary Academy within a 2-week half-term window. The compressed programme required all trades to be mobilised simultaneously and work without gaps, with the school needing to be fully operational on the first day back.

Our Approach

Clarke Lambert Construction pre-sequenced all trades before mobilisation, ensuring that each operation could begin immediately upon completion of the preceding one. Partition removal, structural making good, new partition installation, flooring, ceiling works, and decoration were all programmed to run consecutively within the 2-week window. The site manager conducted daily progress reviews and maintained close communication with the school throughout.

Verified Outcome

Internal remodelling completed within the 2-week programme, delivering reconfigured teaching spaces with new flooring, ceiling upgrades, and full redecoration. The school was handed back ready for the new term with no outstanding items.

Ready to Discuss Your Project?

Clarke Lambert Construction delivers projects like this across the North West. Contact us for a no-obligation consultation, or submit a project brief directly through our Tender Hub.